SYNOPSIS
Today, the demand for technical skills and expertise in Medium Voltage/Low Voltage (MV/LV) electrical reticulation is increasing. It is the responsibility of companies, industries and municipalities to improve and educate their workforce to flow with the technological trend in MV/LV reticulation.
Selections of appropriate MV/LV reticulation philosophy, equipment, cable sizing, fault level calculations, earthing design, protection schemes, etc. are crucial matters that determine any electrical reticulation’s life span. Nowadays, several methods of MV/LV reticulation have been developed, for instance, philosophies like SWER, phase-to-phase systems, single-phase and dual-phase systems have evolved as the most cost-effective systems. However, MV/LV electrical reticulation methods are not always the same in a different environment; therefore, in-depth knowledge of reticulation methods is required by a designer to design a system that will provide maximum return on investment considering capital cost as well as operations and maintenance costs.
This intensive two-day workshop based on appropriate SANS and IEEE standards aims to expound reticulation practices by thoroughly explaining with detailed discussion and real-life practical examples of design, installation, refurbishment, and commissioning of MV/LV electrical reticulation.
Key benefits of attending
- Delegates will be equipped with essential knowledge and state-of-the-art MV/LV reticulation planning, design and design tools, Installations and maintenance.
- Get acquainted with procedures of obtaining fault level calculations and sizing of switchgear
- Learn how to select cable size and types for MV/LV reticulation system
- Imbibe strategy of transformer sizing and selection
- Comprehend the design and application of protection schemes to any MV and LV Reticulation system components
- Understand effective and non-effective earthing to any medium voltage and Low Voltage Reticulation Networks, etc.
- Apprehend and apply appropriate techniques in design and installation of power reticulation within the building including sizing of standby generators
- Enhance your expertise and credibility
Workshop outline
Day 1 module 1
Introduction to MV/LV reticulation
- Life cycle of an electrical network
- Power supply characteristics of medium voltage network
- MV radial network: Single-line service
- MV loop: Ring-main service
- Two parallel MV cables: Parallel feeders service
- Electrical reticulation networks
- Low-cost reticulation systems
- Single-phase, 2-wire feeders with light (small) conductors
- SWS –Shield Wire Systems
- CCS –Capacitor Coupled Substation
Day 1 module 2
ELECTRICAL RETICULATION PLANNING, DESIGN & UPGRADE
- The planning procedure of electricity supply system
- Planning and designing of electricity supply system
- Design and Construction of network assets
- Stages of design
- Maximum demand estimation
- After Diversity Maximum Demand (ADMD) estimation and Load forecasting
- Design tools
- Upgrade of Existing system (MV & LV)
Day 1 module 3
 Fault, Fault Levels calculation and switchgear
- Faults in power system
- What causes short circuit
- What are physical damages from faults
- Why do we perform fault analysis and how?
- Per unit calculation
- Fault level calculation
- Selection of switchgear and cables based on fault levels
Day 2 module 4
MV/LV Reticulation Protection scheme philosophy and selection
- Introduction
- Short circuit performance of protection devices
- Feeders Protection Schemes;
- Transformers Protection Schemes;
- Course activities
Day 2 module 5
 MV/LV Reticulation Earthing
- Introduction to earthing;
- Â Objectives of earthing;
- Functions of earthing systems
- Families of earthing arrangements: TN−S, TN-C, TN-C-S, TT and IT System Earthing
- Different Methods of Power System Earthing;
- Earthing of Equipment installations
- Transformer MV/LV earthing;
- Portable earthing equipment
- Substation earthing
- Â Material for earthing application
Day 2 module 6
Design and Construction of Overhead reticulation system
- Introduction
- What are we designing for
- What physical loadings do we have to allow for our design?
- What physical conditions do we have to allow for in our design?
- How do we allow for all these variable factors in our design?
- Factors in line design
- General Specification for Overhead Electrical Reticulation
- Material selection
- Selection of Insulators; Conductors; Crossarms; Poles; Pole Foundations; Ground Stays
- LV ABC Overhead Lines
- Structure selection guide
- Clearance between MV and LV conductors
- Construction of overhead
- MV and LV Concrete pole orientation layout
- Pole mounted transformers
- Pole Top Boxes (PTB)
- Service Connections
- Metering
Day 2 Module 7
Design and Construction of underground reticulation system
- General Specification for Underground Electrical Reticulation;
- Cable types and cable selection;
- Size and type of load to be supplied
- Permissible voltage drop
- Short circuit ratings of cables
- Environmental Conditions of Installation
- Worked examples of cables selection
- Cable installation methods
Â
Day 2 Module 8
Power Reticulation within a building
- Introduction to power distribution in buildings
- Load assessment and maximum demand
- General power reticulation within building
- Distribution system configuration
- The vertical supply system (rising mains);
- The horizontal supply (distribution at each floor level).
- Incoming supply
- Main switchgear;
- Emergency Generator and UPS
- Final circuit switchgear
- Circuit protective devices
- Cable and distribution
- Final circuit
- Calculations
- Course activities
Day 2 Module 9
Installation commissioning, testing and handover
- Introduction
- Who must have a Certificate of Compliance for electrical installation?
- What is a Certificate of Compliance
- Who is this registered person?
- Inspection and tests
- MV Inspection and test: Testing of the fixed electrical installation, transformers, switchgear, cables, batteries etc
- Documentation
1 Comment
Hi my friend! I want to say that this article is amazing, great written and include approximately all important infos.
I’d like to see more posts lioe this . http://Boyarka-Inform.com/